Hackney to spend £30m restarting Shoreditch Park housing project

The council has appointed Wates Construction for urgent work after the previous contractor collapsed, but the final cost of the 371-home scheme is expected to exceed its revised budget.

Hackney to spend £30m restarting Shoreditch Park housing project – London Altaf Shah

Hackney Council has approved a £30m contract to restart work on the stalled housing development at Shoreditch Park in Hoxton, where 371 homes are planned. Wates Construction will carry out urgent work after the scheme’s main contractor, Ardmore Construction Group, went into administration in June.

The contract covers making the building watertight, buying critical construction materials and managing the site. The council approved it on Monday, November 2. The development is the third and final stage of the Britannia Project, which has already delivered a redeveloped leisure centre and a permanent home for The City of London Academy Shoreditch Park.

The homes were originally due to be finished by the end of 2026, but the timetable following the contractor’s collapse has not been announced. The council says the cost of the development is likely to exceed its revised budget of £196.8m.

What will the homes provide?

The plans include 51 homes for social rent and 30 shared ownership properties. Some of the social rent homes are intended for residents of Colville Estate, whose deteriorating homes are being demolished under a separate regeneration programme.

When Phase 2b was approved in 2023, it was estimated to cost £153.9m. The whole Britannia Masterplan was estimated at £384m when first approved in 2018. The council has not disclosed the value of the revised budget agreed by its cabinet in July.

Why did work stop?

Ardmore entered administration in June 2026 after the High Court imposed a building liability order. The order made the companies liable for £14.9m in historic claims relating to cladding safety.

Hackney’s Cabinet Member for Regeneration, Planning and Inclusive Neighbourhoods, Cllr Alastair Binnie-Lubbock, said further internal works and landscaping would be covered by a second contract award, which would subsume the new deal. The council has not announced the value of that further contract.

Outgoing Executive Director of Housing Rickardo Hyatt said the council had been losing money since Ardmore left the project and that restarting quickly was needed to limit further losses. The £30m award is for the urgent next stage, rather than the full cost of completing the development.

This report draws on information from Yahoo News UK and The Standard.